IronPeak Mining Group · MiningFlagship

Workforce Availability Intelligence: Fit, Qualified, Rostered, On-Site

Maturity
L4
Domain
Plan & Cost
Analytics
predictive
Workforce availability rate
~91%
Sponsor
Chief Operating Officer
Confidence
High

The situation

Shift by shift and site by site, will IronPeak have a fit-for-work, qualified, rostered, on-site crew sufficient for planned production — and where will availability fall short before it happens?

Plan & CostL4Sponsor · Marcus Venter

The recommendation on the table

Stand up site-shift availability forecasting with a pre-shift continuity-risk flag

Production losses anticipated and mitigated days ahead, not discovered when the roster fails.

Decision ownerChief Operating Officer · Marcus Venter
MaturityL4
Priorityhigh

Trade-offRequires roster, attendance, travel, qualification and fatigue data joined reliably at shift grain — the portfolio's hardest integration.

The evidence

IronPeak loses production not because it is under-headcounted but because rostered crews turn out to be unavailable — fatigued and stood down, on leave, travel-disrupted, weather-stranded, or lost to contractor churn — and at a remote site there is no nearby bench. The Mining flagship, MIN-02 forecasts availability — fit-for-work, rostered, qualified, on-site — against production requirements at the roster/shift grain, flags shortfalls before the shift, and optimises rosters and mobilisation. It found swing-change gaps, structural availability erosion from churn and fatigue, and remote sites that cannot mobilise fast enough to fill forecast gaps.

Workforce Availability Intelligence

Match fit-for-work, rostered, qualified, on-site availability to production at the site-shift grain.

Workforce availability rate· site-shifts with fit, rostered, qualified, on-site crew vs. required
~91%+97vs target
Critical
Roster coverage gap· swing-change shifts below required crew (roster-design gap)
~9%
Critical
Availability forecast accuracy· forecast accuracy, contractor-heavy to stable rosters
81–92%
On watch
Mobilization readiness· remote-site gaps fillable within lead-time
~68%+85vs target
Critical
Illustrative preview
Workforce availability rate: site × shift (shortfall intensity)
DayNightSwing-changeWeekend
Pilbara
1
2
3
2
Highlands
1
2
2
2
Lithium-W
2
3
3
2
Underground-E
1
2
2
1

Key takeawayShortfall intensity (3 = frequent). Swing-change shifts run ~9% below required available crew.

Availability loss: structural vs. one-off
100%TOTAL
  • Structural (churn + fatigue + roster)40%40%
  • One-off (travel/weather)60%60%

Key takeaway~40% of one site's availability loss is structural — fixable, not bad luck.

Continuity fragility by site (margin index, lower = fragile)
00.250.50.751PilbaraHighlandsLithium-WUnderground-E

Key takeawayThe remote lithium site runs one disruption from a production loss.

Interactive view is best explored on desktop.

Key findings

Workforce availability — fit-for-work, rostered, qualified, on-site — runs around 91% against plan, with swing-change shifts ~9% below required crew, yet it is the binding production-continuity variable and is almost unmeasured today.

What we can’t claim

About 40% of one site's availability loss is structural (churn, fatigue, roster design) rather than random disruption, and the most remote site can mobilise only ~68% of forecast gaps in time. The inconvenient truth is that establishment, capacity and availability are three different numbers: a site fully staffed on paper can be red on availability, and the fixable losses are the roster and churn ones, not the weather.

Recommendations

Stand up site-shift availability forecasting with a pre-shift continuity-risk flag

high priority

Production losses anticipated and mitigated days ahead, not discovered when the roster fails.

Trade-off

Requires roster, attendance, travel, qualification and fatigue data joined reliably at shift grain — the portfolio's hardest integration.

Redesign the rosters that structurally manufacture availability gaps

high priority

Recovered structural availability and fewer one-disruption-from-loss sites.

Trade-off

Roster change is industrially sensitive and must be done with the workforce, not to it.

Analytical framework

How we reached this

Predictive availability matching — forecast fit-for-work, rostered, qualified, on-site availability and match it to production at the site-shift grain, protecting continuity.

ConfidenceMedium-High

Methods applied

Availability forecastingRoster/coverage modellingMobilization-readiness analysisFit-for-work constraint modellingContinuity/fragility analysis

Statistical techniques

Time-series forecastingSegmentationVariance analysisCorrelationOptimisation

Algorithms

Interpretable time-series forecasting (roster/calendar-aware)Linear-programming roster/mobilisation optimisation under fit-for-work and qualification constraintAvailability-gap classification

Data sources

Rosters/schedulingTime-and-attendanceLeaveTravel/mobilisation logisticsTicket/competency register (qualification)Fatigue stand-down signals (MIN-03)Site access (on-site)Production plans

Outputs generated

Site-shift availability forecasts with bandsRoster-coverage and at-risk-shift outlookMobilisation-readiness viewStructural-erosion analysisContinuity-fragility map

Why this confidence

Roster, leave and attendance data are operational and tractable, giving good forecast accuracy on stable rosters; bounded below High by contractor-churn volatility and travel/weather disruption, shown as widened bands. Fitness and qualification are hard gates.

The reasoning

Business context

The flagship and clearest expression of Mining's thesis: availability — not headcount, not capacity — as the binding production-continuity variable. Availability = Fit-for-Work + Rostered + Qualified + On-Site; a person counts toward a shift only if all four hold. Sponsored by the COO because availability directly determines continuity. It consumes fatigue signals from MIN-03 but does not own fatigue.

Expected value

The largest value pool in the Mining portfolio — avoided production losses from availability gaps, lower premium mobilisation cost, and improved continuity at fragile sites. IronPeak measures equipment availability obsessively and workforce availability barely at all, yet the workforce is the binding continuity variable.

Workforce landscape

Swing-change shifts at two sites run ~9% below required available crew (a roster-design gap); ~40% of one site's availability loss is structural (churn and fatigue); the most remote lithium site can mobilise only ~68% of forecast gaps in time; high-contractor sites forecast to ~81% vs. ~92% on stable rosters.

The analytics journey

Level 4, predictive. Forecasts site-shift availability with confidence and matches it to production under a hard fit-for-work and qualification gate. Honest that contractor churn and travel/weather disruption add variance, shown as widened bands; fitness and qualification are never traded.

Under the hood

Interpretable, roster/calendar-aware time-series forecasting projects availability; linear programming optimises rosters and mobilisation under a fit-for-work and qualification constraint; coverage gaps are classified roster-float / mobilisation / unfillable. Availability is modelled as the conjunction of four gates sourced from four systems — fitness/fatigue, rosters, credential register, and site access.

Confidence & evidence

Why you can rely on this

82%
Analysis confidenceHigh

The inconvenient truth

About 40% of one site's availability loss is structural (churn, fatigue, roster design) rather than random disruption, and the most remote site can mobilise only ~68% of forecast gaps in time. The inconvenient truth is that establishment, capacity and availability are three different numbers: a site fully staffed on paper can be red on availability, and the fixable losses are the roster and churn ones, not the weather.

Method

Confidence is a deterministic read of KPI strength, target and benchmark coverage across this project — shown on an illustrative reference dataset, computed the same way it would be on live data.

Take this further

Where this project connects